ANNUAL OPERATIONAL PLAN 2022/2023
Outcome Functional, efficient and integrated Sector
Output Output Indicator Annual Target Quarterly Target Activities Timeframe Budget per Dependencies Responsibility
Activity
Process the report on Five (5) days R0.00 Minister of Social
findings received from from receipt of Development
the Public Service PSC findings.
Commission by drafting
letters to relevant SMS
members to request
reasons as to why they
did not disclose all their
registrable interests.
Summary report on Five (5) days R0.00 Dir: Labour Rela-
non-compliance to Dir: from receipt of tions
LR reasons pro-
vided by SMS
members
Dir: LR submit a final Ten (10) days R0.00
report on steps taken to from receipt of
the EO. the summary
report from the
Ethics Unit
Draft and submit a letter Thirty (30) days R0.00
addressed to PSC to the from receipt of
Minister for signing indi- findings from
cating disciplinary steps PSC.
taken against relevant
SMS members.