PART B: PERFORMANCE INFORMATION                                                                                                 PERFORMANCE BY PROGRAMME



        Information Management Systems and Technology
         Outcome   Functional, efficient, and integrated sector
         Output   Output      Actual Achieve- Actual Achievement 2020/21       Annual              Actual Output 2021/22   Reasons for Deviation from 2021/22 target
                  Indicator   ment 2019/20                                     Target 2021/22
         DSD      DSD         N/A          As part of implementing Sector ICT Strategy,  Develop Substance   Service provider was   The delayed procurement processes and crafting
         Integrated  Integrated            the Department developed two (2) modules   Abuse System into   appointed for the   of the contract led to delays in development of
         Social   Social                   on Social Development Integrated Case   SDICMS          development of the system   the system hence it was not finalised according
         Protection  Protection            Management System (SDICMS), namely; the                 which will be finalised and   to plan.
         System   System                   Older Persons Abuse Register module and                 rolled-out throughout the
                  implemented              the Accreditation of Division Services and              country in June 2023.
                              N/A          Quality Assurance module.           Integrate VEP and GBV  VEP and GBV systems fully   No deviation
                                           A service provider was also appointed   systems         integrated.
                              N/A          to assist with the integration of Gender-  Develop Alternative   Enterprise architect and   There was a misalignment in the timelines for
                                           Based Violence (GBV) Victim Empowerment   Care Management   system prototype for   deliverables within the contract signed with the
                                           (VEP) Systems, which is also part of the   System into SDICMS  Alternative Care Management  service provider for twenty-four (24) months
                                           implementation of the Sector ICT Strategy               System have been completed.  (ending March 2023) as opposed to the APP
                                                                                                                           commitment of developing he System by March
                                                                                                                           2022, hence the system development was not
                                                                                                                           completed.
         Strategies to overcome under performance
            ·   The development of the Substance Abuse System into SDICMS will be finalised and rolled-out throughout the country in June 2023.
            ·   The development of the Alternative Care Management System into SDICMS will be completed in March 2023.